The brickies finished off their work this week. Summary as follows -
Monday 29th Oct - brickwork
Bedroom 1 and the walk-in robe
finished corbel at front of house RHS, and the flashing over the garage
support beam in front of the garage, and the nearly complete wall at front
Tuesday 30th Oct - brickwork
view from below, and the walk-in robe again
bedroom 3 and 4
support beam (middle) and outside on the patio
patio shots including building the patio wall over entrance
down the LHS (from front)
down the LHS and showing the flashing to roof over garage from inside wall (main BR)
Roof trussing fun!
Wednesday 31st Oct - brickwork
View from entrance and the finished 'box' over entrance - there's a roof in there! Weird!
More views of the front entrance box, from the patio
The box
Thursday - no activity apart from sweeping, updated photos without sunglare below -
As it stands today
Final finish front and LHS
Close-up of intended gab between corbel and roofing and view from front
Friday - no activity, apart from receiving the bricking phase completion invoice! $66K.
As of Monday morning (5th Nov), there has been no further activity - expecting the guttering and roof, but I'm only guessing, as the site supervisor is MIA.
What really irks me is that we waited 8 weeks with no activity, and then the bricks only took 3-4 days to complete... and then we're back to waiting again for who knows what....
No comments:
Post a Comment
Hi! Thanks for your comment!
It has been forwarded to the site administrator for approval.
If it isn't spam, it will be published, unless you've requested otherwise.
Thanks for contributing to the site!