Monday, 5 November 2012

This weeks update

The brickies finished off their work this week. Summary as follows -

Monday 29th Oct - brickwork

Bedroom 1 and the walk-in robe


finished corbel at front of house RHS, and the flashing over the garage


support beam in front of the garage, and the nearly complete wall at front


Tuesday 30th Oct - brickwork

view from below, and the walk-in robe again


bedroom 3 and 4


support beam (middle) and outside on the patio


patio shots including building the patio wall over entrance


down the LHS (from front)


down the LHS and showing the flashing to roof over garage from inside wall (main BR)


Roof trussing fun!


Wednesday 31st Oct - brickwork

View from entrance and the finished 'box' over entrance - there's a roof in there! Weird!


More views of the front entrance box, from the patio


The box



Thursday - no activity apart from sweeping, updated photos without sunglare below  -

As it stands today


Final finish front and LHS


Close-up of intended gab between corbel and roofing and view from front

 


Friday - no activity, apart from receiving the bricking phase completion invoice! $66K.

As of Monday morning (5th Nov), there has been no further activity - expecting the guttering and roof, but I'm only guessing, as the site supervisor is MIA.

What really irks me is that we waited 8 weeks with no activity, and then the bricks only took 3-4 days to complete... and then we're back to waiting again for who knows what....

No comments:

Post a Comment

Hi! Thanks for your comment!

It has been forwarded to the site administrator for approval.

If it isn't spam, it will be published, unless you've requested otherwise.

Thanks for contributing to the site!