So here's a photo, after the site rubbish was removed, on the morning of PCI.
Inside, the ensuite now has the correct shower rose -
Also in the ensuite, we now have a strange ugly long bath spout - hey at least it reaches the bath now. But look! There's some tile damage - noted with SS, but not sure if on PCI sheet...
Here's the kitchen, with half-complete splashback, on PCI day -
SS reckons this brick is normal, above alfresco. Not so sure. And a drill mark in the rear wall, needs repairing -
I took a photo of the run-sheet. It would've been nice to have seen some of these dates or known what the progress steps were, along the way. It might be useful for other readers that are building -
Yesterday, I came by at lunchtime to find a digger and a new power-pole in the midst of being installed -
Here's the trench, and the pole. They use the cardboard ring to encapsulate the concrete support, then I guess it breaks down (?) -
The fuse-box innards, and a shot of underneath the fusebox -
Looks like during the digging they smashed into the charged stormwater piping - oops! And as I was taking photos, a truck pulls up, containing a couple of very disgruntled workers, pissed off that they weren't told about the piping being there in the first place. Lessons learnt, Masterton? Speak with your tradies!
Here's the complete splashback -
More on the fusebox, this time completed, as of Monday 25th afternoon -
Top of power-pole, and the house at 5:00pm -
OK, so here's today's morning shots. The blackbutt flooring is being installed -
Media room intensity -
Another new update this afternoon. The landscaping of the rear yard has commenced, and the flooring should be complete. Also the storm fencing should be removed this afternoon as well.
Thus endeth this post.
No comments:
Post a Comment
Hi! Thanks for your comment!
It has been forwarded to the site administrator for approval.
If it isn't spam, it will be published, unless you've requested otherwise.
Thanks for contributing to the site!