Wednesday, 29 August 2012

Plumbing, Brickwork continues

Sewage runs for main bathroom completed today - run goes through void in laundry.

More brickwork yesterday and today occurred.

The front facade is higher and side walls are growing tall. RHS below.


 LHS media room window being bricked around.


urgh... DUX hot water system insert installed yesterday.


rear view and LHS from rear view


Alfresco shots. Rear stairs not happening until after keys and handover. Stubborn rule-following unimaginative site supervisor.


Crack in alfresco sliding door wooden outer frame... not sure how they'll fix that! and staircase nearly bricked in


shot of plumbing runs in office and window shot in office

 
garage wall shot

No comments:

Post a Comment

Hi! Thanks for your comment!

It has been forwarded to the site administrator for approval.

If it isn't spam, it will be published, unless you've requested otherwise.

Thanks for contributing to the site!