Saturday, 2 February 2013

Kitchen & Lockup Update (MAJOR)

Lockup achieved 1st Feb 2013, after a false start the day before.

Lots of progress. Kitchen fitted. All doors fitted. Most architraves and skirting fitted. Upstairs verandah sliding doors re-fitted after waterproofing.

Some issues with the kitchen, but all-in-all happy with progress. No show-stoppers.

Sorry about the poor photos - it was raining down like crazy outside. In fact, a sizey tree branch fell on my car bonnet today and make a large dent I'm going to have to have panel-beaten and re-sprayed.

First up, it seems some more brick-work is necessary. The overhead beam in the garage had this note on the inner side.



Skirting is done in the garage, and the internal access sold-core door is fitted. (note the incorrect sizing on the door frames - this was the cause of one weeks delay last week due to incorrect draft-plan vs what's in contract) -



 Here's the powder room, with vanity and door in place, ready for tiling -


Hallway to Great Room / kitchen, with doors fitted to understairs, pantry and laundry, ready for tiling -


Panoramic of the kitchen -


Kitchen shots -


Inside the under-sink unit, keen to keep that shelf - we'll see!


More kitchen, including a severely damaged drawer fascia in the kitchen island bench -


Kitchen from corner of Great Room, and the main bathroom vanity unit -


Bedroom 2 complete - they all look the same -


Main Bedroom and ensuite vanity, ready for tiling -


 A downstairs window was open - naughty naughty!

4/2/13 EDIT: the coming week should see a plethora of tilers onsite. Skirting upstairs around windows, and architraves in media room remain, otherwise painting can commence also.

No comments:

Post a Comment

Hi! Thanks for your comment!

It has been forwarded to the site administrator for approval.

If it isn't spam, it will be published, unless you've requested otherwise.

Thanks for contributing to the site!